Working a live project control path?
Request project reviewNew to this workspace?
Follow the production-to-LD control path in under five minutes.
Northline Grid + Data Zone · Sep 11, 2026
Project control room
Rules of credit active
Physical field work earns auditable installed credit by approved production step.
Installed
50.7%
Portfolio credit-weighted progress
Production factor
0.91
Earned hours ÷ actual hours
LD exposure
$160,000
MC / SC / COD production forecast
Open approvals
4
Production, quality, notices
Production units
Approved credited quantities are the shared source for schedule, forecast, and milestone metrics.
Foundation Piers
CIV-100 · EA · 81.3% credited
1,008 / 1,240 EA
Forecast Sep 30, 2026
PF 0.93
Structural Steel
STR-200 · TON · 64.8% credited
2,840 / 4,380 TON
Forecast Dec 4, 2026
PF 0.95
Electrical Ductbank
ELE-300 · LF · 31.2% credited
36,800 / 118,000 LF
Forecast Dec 17, 2026
PF 0.77
Equipment Setting
ELE-410 · EA · 25.6% credited
42 / 164 EA
Forecast Dec 16, 2026
PF 1.11
Contract milestones
Forecasts update from credited production rates.
MC · Dec 4, 2026
Forecast +4 days · AT RISK
Contract Nov 30, 2026
$160,000 exposure
SC · Dec 17, 2026
1 days early · ON PLAN
Contract Dec 18, 2026
$0 exposure
COD · Dec 29, 2026
13 days early · ON PLAN
Contract Jan 15, 2027
$0 exposure